Case Study: M&E Design and Installation
Scope of Works:
- Act as Principle contractor
- To design and install new high bay bus bar electrical distribution
- To design and install Gas heating system and strat fans
- To design and install new electrical distribution containment
- To design and install high bay lighting system
- To design and install all emergency lighting system and escape strategy
- To supply and install industrial floor coverings and epoxy floor paint
- To design, supply and install new external compressor housings
- To design and install new hard standings for external specialist gasses
- To supply and install new fencing and safety segregation areas
- To Supply and install new access control system
Location: Derbyshire
Duration: 25 Weeks
Value: £1.5m