Case Study: Office Suites
Scope of Works:
- Act as Principle contractor
- To design, specify and install a new mixed use office facility
- Design office layout to accommodate three businesses consolidating into one facility
- To supply break out and canteen areas
- To supply various meeting areas and boardroom facilities
- To Strip out part complete base build interior and extend offices 200% to accommodate 125 staff
- To provide disabled facilities and future proofing
- To supply new raised access flooring
- To supply and install all new partitioning and fire breaks
- To insulate to achieve a ECP or B or better
- To design and install 8m x 65m 2 hour fire wall complete with all doors
- To install new fire alarm system
- To install full access control system
- To design and install new staircase balustrade
- To supply and install all new floor coverings
- To supply and install all desks, seating and storage solutions
- To Design supply and install all new ventilation and comfort cooling and AC
- Installation of conference room facilities
- Design and installation of all Data cabling CAT6e
- Design and install a new comms room facility and cooling
- Supply Comms racks and power solutions to Comms room
Location: Derbyshire
Duration: 20 Weeks
Value: £575k