Scope of works:
- Act as Principle contractor
- To develop the planning application with the local authorities
- To extend the existing paint shop facility to remove the hazard risks from the local area
- To prepare the sub floor and ground in preparation for a new single story steel frame paint mixing area
- To supply and install a suitable steel framed structure to seamlessly extend current facility and to ensure clients facility is within planning application guideline
- To link the steel structure to the existing building and match the external aesthetics
- To supply a clean room environment with explosion venting and IP65 lighting
- To ensure all works satisfy FM Global requirements
Location: Buckinghamshire
Duration: 7 Weeks
Value: £75k